Jubilant Infrastructure Limited
Gujarat,?India
3 X 5 MW Natural Gas?Power Plant?(Gas?Tribune)
Dismantling
Lifting & Transportation
Installation
PetroChina Company Limited
Basra, Iraq
3 X 1,8 MW Crude Oil?Pump
Installation
Altaca Insaat Power Plant
Attrau, Kazakhstan
Company Profile:
Altaca Insaat A.S. is one of the well known and reliable construction companies located in Turkey. The company constructs buildings in Kazakhstan and Russia region. Altaca constructed a residence building with 250 kWh power demand in Attrau.
Cogeneration powerplant:
The co-gen unit Lindenberg CHP 250 is formed of 1 pc. of MAN E 2842 E 312 (250kW) gen-set and the heat recovery equipment. The system is under operation since 2007.
Waste Heat Recovery :
The recovered waste heat of the gen-set is used for the building heating. All the heat in the exhaust and jacket water of the engine is recovered by means of hot water through heat exchangers.
Ciment de Mauritania Power Plant
Nouakchott, Mauritania
Company Profile:
Ciment de Mauritania is one of the largest capacity cement factory ,which is located in the capital city, Nouakchott.
Cogeneration powerplant:?
Complete powerplant has been dismantled ,packed ,erected and commissioned by DAS Energy with Turkish people. Tanks, compressors, radiators and some other auxilary equipment are calculated and provided by DAS Energy for Ciment de Mauritania from Turkiye.
Waste Heat Recovery :
Danstoker boiler provides the demands of steam by using the waste heat of the exhaust and jacket water heat of the HFO burning 18V 28/32 MANb&W diesel engine is providing the hot water demands of the factory.By this way maximum efficiency is obtained.Thus,no additional cost is calculated for steam and hot water generation.